Update Lely Campus Phase 2
31/05/2021 |
Maassluis
Due to the continued worldwide growth of Lely’s business activities, the current facility will be doubled, with three wings of office space totaling 10,600 m2 and a production hall totaling 24,000 m2. Construction of the new facility is on schedule and is expected to be completed in the first quarter of 2022. With sustainability as a top priority, the farming innovator is striving for a ‘BREEAM Outstanding’ certification, just like with the current building.
Some milestones of the new building
- June 2019: Start of demolition work of the old production halls and office space
- March 2020: Start decontamination of the site
- July 2020: First pile of new building
- October 2020: Start placement of foundations
- November 2020: Construction of steelwork
- January 2021: Placement of connecting bridge from existing building to new building
- February 2021: Landfill of floors
- April 2021: Installation of glass outside walls